HARBOR-UCLA MEDICAL CENTER

Torrance, California

Expanding from 1,280,000 sq ft to 2,457,000 sq ft
$322 million

Project Description

David Fernandez, then the Senior Project Manager for gkkWorks, was the onsite executive responsible for the Construction Management Team, which oversaw the design and construction of this multi-phased design-build project. David Fernandez was responsible for the Construction Management Team of fifteen personnel that included project / construction managers, estimators, schedulers, medical equipment coordinators and project administrative staff. This team oversaw both the design and construction of this complicated project. The project budget was at risk on many occasions, but with David’s leadership, the project closed out on schedule and well under budget.